271GB. Penalty for failure to furnish report or for furnishing inaccurate report under section 286—  (1) If any reporting entity referred to in section 286, which is required to furnish the report referred to in sub-section (2) of the said section, in respect of a reporting accounting year, fails to do so, the authority prescribed under that section (herein referred to as prescribed authority) may direct that such entity shall pay, by way of penalty, a sum of,—

(a) five thousand rupees for every day for which the failure continues, if the period of failure does not exceed one month; or

(b) fifteen thousand rupees for every day for which the failure continues beyond the period of one month.

(2) Where any reporting entity referred to in section 286 fails to produce the information and documents within the period allowed under sub-section (6) of the said section, the prescribed authority may direct that such entity shall pay, by way of penalty, a sum of five thousand rupees for every day during which the failure continues, beginning from the day immediately following the day on which the period for furnishing the information and document expires.

(3) If the failure referred to in sub-section (1) or sub-section (2) continues after an order has been served on the entity, directing it to pay the penalty under sub-section (1) or, as the case may be, under sub-section (2), then, notwithstanding anything contained in sub-section (1) or sub-section (2), the prescribed authority may direct that such entity shall pay, by way of penalty, a sum of fifty thousand rupees for every day for which such failure continues beginning from the date of service of such order.

(4) Where a reporting entity referred to in section 286 provides inaccurate information in the report furnished in accordance with sub-section (2) of the said section and where—

(a) the entity has knowledge of the inaccuracy at the time of furnishing the report but fails to inform the prescribed authority; or

(b) the entity discovers the inaccuracy after the report is furnished and fails to inform the prescribed authority and furnish correct report within a period of fifteen days of such discovery; or

(c) the entity furnishes inaccurate information or document in response to the notice issued under sub-section (6) of section 286,

then, the prescribed authority may direct that such person shall pay, by way of penalty, a sum of five lakh rupees.